DVW Adjustments
Posted: Mon Dec 29, 2025 8:48 am
This was taken from the original BroadcastTech.NET web site in 2002
DVW Adjustments:
After Head replacement
In order to perform a full adjustment it is recommended that you have the Service Manual available.
Also Tape Path and RF adjustments MUST be completed and correct.
CTL Head Height
Alignment Tape - ZR2-1
Test Point - TP800 (SS-52 Board) CTL Signal
TP819 (SS-52 Board) TRIG
Adjustment - Adjust level until the highest point
CTL Position Adjustment
Alignment Tape - ZR2-1
Test Point - TP2801 (SS-52 Board) SAT ENV Signal
TP819 (SS-52 Board) TRIG
TP101 (EQ-45 Board)
Adjustment - Adjust so that marker on TP2801 signal is aligned on the lower section of the TP101 waveform and the upper section of the TP819 waveform.
Audio/TC Height Adjustment
Alignment Tape - ZR2-1 (TC 00:00:00 to 15:00:00)
Test Point - CUE output. Scope either the + or -.
Adjustment - Adjust level until the highest point.
Audio/TC Azimuth Adjustment
Alignment Tape - ZR2-1 (TC 15:00:00 to 25:00:00)
Test Point - CUE output. Scope either the + or -.
Adjustment - Adjust level until the highest point.
Audio/TC Head Position Adjustment
Alignment Tape - ZR2-1 (TC 00:00:00 to 15:00:00)
Test Point - TP815 (SS-52 Board) CTL Pulse Signal
TP2800 (SS-52 Board) PB LTC signal TRIG
Adjustment - Adjust so that the rising portion of the two waveforms are in line.
Audio Level Adjustment in REW Mode.
Alignment Tape - ZR2-1 (TC 00:00:00 to 15:00:00)
Test Point - CUE output. Scope either the + or -.
Adjustment - Put unit into REW X1 Mode. Check audio level
-Put machine in Play mode. Check audio level
Audio levels should be the same.
If not the same there is a tape path problem.
Re-do tape path.
(Last updated Aug 16 2002)
DVW Adjustments:
After Head replacement
In order to perform a full adjustment it is recommended that you have the Service Manual available.
Also Tape Path and RF adjustments MUST be completed and correct.
CTL Head Height
Alignment Tape - ZR2-1
Test Point - TP800 (SS-52 Board) CTL Signal
TP819 (SS-52 Board) TRIG
Adjustment - Adjust level until the highest point
CTL Position Adjustment
Alignment Tape - ZR2-1
Test Point - TP2801 (SS-52 Board) SAT ENV Signal
TP819 (SS-52 Board) TRIG
TP101 (EQ-45 Board)
Adjustment - Adjust so that marker on TP2801 signal is aligned on the lower section of the TP101 waveform and the upper section of the TP819 waveform.
Audio/TC Height Adjustment
Alignment Tape - ZR2-1 (TC 00:00:00 to 15:00:00)
Test Point - CUE output. Scope either the + or -.
Adjustment - Adjust level until the highest point.
Audio/TC Azimuth Adjustment
Alignment Tape - ZR2-1 (TC 15:00:00 to 25:00:00)
Test Point - CUE output. Scope either the + or -.
Adjustment - Adjust level until the highest point.
Audio/TC Head Position Adjustment
Alignment Tape - ZR2-1 (TC 00:00:00 to 15:00:00)
Test Point - TP815 (SS-52 Board) CTL Pulse Signal
TP2800 (SS-52 Board) PB LTC signal TRIG
Adjustment - Adjust so that the rising portion of the two waveforms are in line.
Audio Level Adjustment in REW Mode.
Alignment Tape - ZR2-1 (TC 00:00:00 to 15:00:00)
Test Point - CUE output. Scope either the + or -.
Adjustment - Put unit into REW X1 Mode. Check audio level
-Put machine in Play mode. Check audio level
Audio levels should be the same.
If not the same there is a tape path problem.
Re-do tape path.
(Last updated Aug 16 2002)